WE Energies Upgrades

WE Energies Upgrades

2020-06-18T13:23:11-05:00June 18th, 2020|E-News|
WE Energies will install three electrical pad-mounted transformers on UUCW property within the south tree line.
WE Energies has contacted UUCW requesting an additional easement to connect the electrical service to North Avenue. WE Energies will be installing three additional single-phase pad-mounts that will serve residents to the south of our property. This will eliminate the overhead electrical lines that run along the south side of our property. This will also eliminate future tree trimming requirements. The locations are currently staked out and include two pad-mounts to the west of the building and one to the east. All of the pad-mounts are located within the south tree line. The Executive Team has approved the easement request.
If you have any questions, please contact Vicki Banville, Church Administrator.